Wednesday, August 12, 2009

DAY 37

Okay, as posted we said we were having a bit of a row with the contrator. We were assured by the partner that they would finish up yesterday (Tuesday). Well, they got most done, but didn't quite finish.

All of the siding is now done....


...but they didn't finish the front gutter or finish the moulding.


I'm a little leary of the way they are just covering the dental moulding. I was under the impression they were taking it off. If they were clearer about covering it I would have got up there one last time and painted it again to help seal it. Oh well, nothing for it now.

Kristen had a final walkthrough this morning (Wednesday) and listed out all the items we had issues with. They are supposedly correcting them today once they finish the moulding and gutter work.

Top-soil was also delivered today, but the Bobcat hadn't arrived by the time Kristen left. Hopefully they got all cleaned up and the Bobcat has arrived and they are putting down the new topsoil and re-seeding.

Called to have the dumpster removed and could take up to 5 days or so before they can get out to get it. Of course the contractor said they could also come at 4am tomorrow to get it as well. We just won't know until it's gone.

No comments: